Skip to the reportSkip to report

As of 2026-08-13 · pulled 13 Aug 2026, 23:31 (same day as the last Jira change)

5,215 work items across four squads.

SummaryJira

No thresholds declared

40% of delivery work has passed QA, 1474 items are in flight, and 5 have reached SIT or beyond.

  • “Delivered” means development complete and QA passed. 494 of these items have since been released to production; the rest are not released — SIT, pre-production and release all come after it.
  • No issue links are recorded for Value Add, so an empty dependency row means not recorded rather than not blocked.
Delivered

Development complete and QA passed. Not released.

Delivered

40%

2075 of 5215 work items

Completed in sprint 18

Work items whose completion date falls in sprint 18. The comparison is against sprint 17, which is complete, so part of the gap is time not yet elapsed.

Completed in sprint 18

75

Sprint 18 is still running

▼ 40 vs sprint 17

Carry-over

Sprint 17, the last completed sprint. In its final scope, not finished when it ended, and in a later sprint.

Carry-over

87%

731 of 843 in sprint 17 scope

▲ 3 vs sprint 16

Commitment reliability

Completed on or before the due date.

Coverage. 1740 of 2075 completed items carry a due date

Commitment reliability

41%

707 of 1740 completed with a due date

Coverage 84%

Released to production

Items with a recorded transition into the Production phase, at any point. Not items sitting in it now — released work moves on to Complete, so the current count is zero and always will be.

Released to production

494

of 5215 work items · 568 across the programme

Items blocked

Unfinished work items on the receiving end of a Blocks or Depends link.

Coverage. See dependency coverage by squad

Items blocked

377

5 blocked by another squad · 98 from outside the four

40% past QA, 0 in production nowJira

779 stories, and how they moved through the workflow
How to read the workflow, and what it does not say
Every status the Jira workflow configures, in the order work walks them, for user stories only — Task and Technical Task run a workflow with no test gates, and mixing them made 88% of the apparent skips artefacts of the mix. A CIRCLE IS HOW MANY STORIES SIT THERE NOW. Filled means work is there; a tinted ring means work has been there and moved on; a dashed grey ring means no story has ever entered. That is why the release run reads zero and still shows traffic — nothing sits past QA test passed today, and stories have walked every status through to production. The chip beside each name is that status's own code, unique across the workflow so it identifies exactly one status wherever it is quoted, and coloured by its lifecycle phase so the eight groups still read at a glance. The legend below the diagram spells out all 28. A LINE TAKES THE COLOUR OF THE STATUS IT LEAVES, so a return is traceable to where it came from without following it. The main path is one constant width and the widest thing here; everything off it is thinner and weighted by how many moves took it. A dashed line with no motion is a route the workflow configures that no story has ever taken. Everything that fails, parks or reverts returns to In Triage or To Do, which is why those share one line back rather than six. No duration is shown anywhere on this diagram. 56% of status transitions in this project are zero-elapsed back-fill, so any median would measure when a status was typed rather than when work moved.
8389135128058212300000000070208000000
GRGathering requirements
TRIIn Triage
TODOTo Do
DEVIn Development
PRVPeer review
RQAReady for QA
QATQA Testing in process
QAPQA test passed
REGIn regression testing
RSITReady for SIT
DSITDeployed to SIT
RPPReady for PreProd
DPPDeployed to PreProd
ARELApproved for release
SCHScheduled for release
PRODReleased to production
MONMonitoring
CMPComplete
RRVReady for review
IRVIn review
APVApproved
HLDOn hold
REOReopened
QAFQA test failed
REGFRegression failed
SITFSIT failednever used
PPFPreProd failednever used
RBKRollback

Definition399

  • GRGathering requirements8
  • TRIIn Triage389
  • RRVReady for review0
  • IRVIn review2
  • APVApproved0

Ready135

  • TODOTo Do135
  • REOReopened0

Development128

  • DEVIn Development128
  • PRVPeer review0

QA79

  • RQAReady for QA58
  • QATQA Testing in process21
  • QAFQA test failed0

Done30

  • QAPQA test passed23
  • CMPComplete7

SIT & Regression0

  • REGIn regression testing0
  • RSITReady for SIT0
  • DSITDeployed to SIT0
  • REGFRegression failed0
  • SITFSIT failednever used

Pre-production0

  • RPPReady for PreProd0
  • DPPDeployed to PreProd0
  • ARELApproved for release0
  • SCHScheduled for release0
  • PPFPreProd failednever used

Production0

  • PRODReleased to production0
  • MONMonitoring0
  • RBKRollback0

No single phase8

  • HLDOn hold8

User stories only — 779 of them, across the workflow's 28 statuses, with 1,495 moves between them. Task and Technical Task run a workflow with no test gates and are counted in the bar above but not here. The number in a circle is how many sit there NOW, not how many have passed through. Each chip is that status's own code, unique across the workflow so it can be quoted elsewhere, and coloured by its lifecycle phase. 76 moves went backwards and 70 left the road for a parked, failed or reverted state; every one of those returns to In Triage or To Do, which is why they share one line back.

The same distribution, per squad
What each column measures
Reliability is of completed items carrying a due date, so its coverage sits beside it: the squads run from 78% to 96%, and the same percentage over different denominators is not the same claim. Blocked counts unfinished items on the receiving end of a Blocks or Depends link; Relates is association, not constraint.
SquadItemsQA passedDone in sprint 18Commitment reliabilityDue-date coverageBlocked
Everyday Banking2,20045%2027%77%388
Cards & Lending1,80230%1347%88%151
Payments & Transfers94157%4255%95%85
Value Add2728%0no due dates0%not recorded

Sprint deliveryJira

Scope, reconciled · from Jira
An identity, not four measurements
Start plus added minus removed equals final, and it holds because added and removed are defined from the two boundary states rather than from raw join and leave events. An item that left and came back is committed scope that churned, not new scope. A build where they do not add up fails rather than renders.
Completed so far · from Jira
Counted from the completion date
Not the Sprint field. Stories are bulk-moved onto the active sprint, so the field would credit old completions to whichever sprint is running now.

75of 1,118 in scope

Sprint 17 finished 115. Sprint 18 has not ended, so the gap is partly time not yet elapsed.

494 items released to production, 47% of R1 past QAJira

R1 — 47% past QA
QA passed, not released
Counts items at the last lifecycle phase. Some has since been released and the Summary carries that count, but this bar measures work that cleared development and test, not work that left the release chain.

1,621 of 3,466

R2 — 1% past QA
QA passed, not released
Counts items at the last lifecycle phase. Some has since been released and the Summary carries that count, but this bar measures work that cleared development and test, not work that left the release chain.

4 of 311

R3 — 4% past QA
QA passed, not released
Counts items at the last lifecycle phase. Some has since been released and the Summary carries that count, but this bar measures work that cleared development and test, not work that left the release chain.

5 of 137

1,301 carry no release

In none of these bars, and counted in the page total rather than distributed by guess.

The 10 epics carrying the most unfinished work
Ranked by open children, not by percentage
An epic at 20% with four children is a rounding error. Furthest phase reached is computed from the children IN SCOPE, so narrowing to a release changes it. Childless epics are excluded: a list about where the work is cannot be padded with epics carrying none.

The 10 epics with the most unfinished work, of 188 carrying any. 843 items are open across all of them.

EpicSquadOpenChildrenQA passedFurthest phase reached
NILE-9168Technical EPIC - Payments and TransfersP&T11618838%QA passed
NILE-158Transfers - Add/Manage Beneficiaries (MOCK)P&T399459%QA passed
NILE-84Debit Cards - Card Activation (MOCK)CL225761%QA passed
NILE-107Personal Loan (Secured) - Apply - Inputs (MOCK)CL20200%QA
NILE-133Credit Cards - Manage Card Limit (MOCK)CL19190%Development
NILE-121Credit Cards - Apply for Credit Card (Unsecured) (MOCK)CL15150%Development
NILE-2219Credit Cards - Apply for Credit Card (Secured) (MOCK)CL15150%Development
NILE-2210Debit Cards - Freeze/Cancel Card (MOCK)CL136480%QA passed
NILE-52Login - Forgot/Reset Credentials (MOCK)EDB134470%QA passed
NILE-2239Accounts Lifecycle Management - Flagged Account StatusesEDB13130%Definition

7 of the 16 open R1 activities are behind their own line, and ARB approved for Payments & Transfers is 55 points behind itManual entry

Where each release stands
Read a row across; the counts do not compare down
Within one kind of work the unit is the same in every release, so R1 build and R2 build compare. The COUNTS do not compare down a column: test cases run in the thousands where solution designs run in the tens, which is why there is no total. The SHARES do, and the bar draws the share rather than the count.
Kind of workRelease 1Release 2Release 3
Elaboration712 of 712100%348 of 44079%not started
Design gate86 of 12370%not startednot started
Build589 of 75578%not startednot started
Platform APIs0 of 50%not startednot started
Test cases4,332 of 6,19470%not startednot started
What was committed, and what arrived
Commitment against delivery, one kind of work per chart
The outline is what the squad signed up to at the start of the sprint; the solid bar is what it delivered. One kind of work per chart, because the units differ. Sprints are not slices of a total: work not finished is committed again next sprint, so these columns must never be added up.

Committed at the start of each sprint against what arrived. Both charts share one scale, so a bar in either stands for the same number of items.

CommittedDelivered

Build

12345678910111213141516171819

Design gate

131415161718
What is still open, and when it is due
Progress against the plan’s own line
Only activities incomplete against their own plan, grouped by the revised target they are working to. The gap is the share delivered minus the share of that activity’s window that has gone, both from the plan. An activity with no committed sprint has no window and shows no gap rather than a made-up one.

2026-09-014 of 6 behind their line

  1. ARB approvedP&Twell behind
  2. Experience APIsP&Twell behind
  3. Integration APIsP&Tbehind
  4. Front-end screensP&Tbehind
  5. Test casesP&Ton its line
  6. Test casesCLahead

2026-09-263 of 10 behind their line

  1. Experience APIsEDBwell behind
  2. ARB approvedCLbehind
  3. Integration APIsEDBbehind
  4. Experience APIsCLon its line
  5. Cyber reviewedCLon its line
  6. Front-end screensEDBahead
  7. Integration APIsCLahead
  8. Test casesEDBahead
  9. ARB approvedEDBahead
  10. Platform APIs: NICLno window

Measured against the plan’s own line. The bar is the share delivered; the tick is the share of that activity's own window that has gone, from its first committed sprint to its revised target. Both come from the plan. The gap between them is the number. The only judgement is where it becomes a word: behind past 5 points, well behind past 20.

Every activity the plan tracks
Delivered of committed, and what a dash means
On one sprint a cell reads as what the squad committed to on day one against what it finished. On all sprints it reads as progress against the whole plan. Over 100% is real and is not capped: a squad can finish more than it committed to. A dash is a row the plan holds with nothing committed; a dot is a row the squad does not have.
ActivityEveryday BankingCards & LendingPayments & TransfersValue Add
Elaboration
Regulatory review143 of 143 100%125 of 125 100%75 of 75 100%13 of 13 100%
UI/UX and customer journey29 of 29 100%31 of 31 100%15 of 15 100%3 of 3 100%
User stories114 of 114 100%94 of 94 100%60 of 60 100%10 of 10 100%
Design gate
ARB approved8 of 11 73%4 of 22 18%1 of 8 13%
Cyber reviewed11 of 11 100%13 of 22 59%8 of 8 100%
Solution design finalised11 of 11 100%22 of 22 100%8 of 8 100%
Build
Experience APIs37 of 71 52%18 of 22 82%42 of 63 67%
Front-end screens150 of 168 89%144 of 144 100%84 of 109 77%17 of 17 100%
Integration APIs27 of 62 44%47 of 64 73%23 of 35 66%
Platform APIs
Platform APIs: NI·0 of 5 0%·
Platform APIs: Payment Hub···
Platform APIs: T24··
Platform APIs: TPH···
Test cases
Test cases1,528 of 2,301 66%1,519 of 1,984 77%1,285 of 1,909 67%
Test cases including the deep layer

Squad and activity totals, not individual artefacts. The source is an aggregate grid, so this section cannot be drilled into.

PredictabilityJira

Carry-over
All three conditions, on a completed sprint
In the sprint’s final scope, not finished when it ended, and in a later sprint. Not “in more than one sprint” — an item can sit in two because someone corrected a field. Measured on completed sprints only: in a running sprint nothing has moved on yet and the figure reads near zero, which says carry-over is solved.

87%731 of 843 in sprint 17 scope

100%50%87%
  1. S12
  2. S13
  3. S14
  4. S15
  5. S16
  6. S17
Commitment reliability
Two denominators, named
Of completed items carrying a due date, the share that finished on or before it; items completed without one are excluded from both halves rather than counted as met. The headline is every completed item to date and the line is each sprint’s own completions, so the endpoint and the figure above it are different measurements.

41%707 of 1740 completed with a due date

100%50%53%
  1. S12
  2. S13
  3. S14
  4. S15
  5. S16
  6. S17

1740 of 2075 completed items carry a due date. The line is each sprint's own completions, the figure above is every completed item to date.

14% of work that reached Development came back to itJira

Development rework
Phase re-entries, not status hops
A move between two Development statuses is work continuing, not rework. The denominator is items that ever reached Development, so leaving work in Definition cannot improve the figure.

14%397 of 2,890 that reached Development

Nothing is ranked for attention, and why

Waiting on declared thresholds, not on build time. Solution Design’s 14 and 30-day bands are that page’s, not this one’s.

Where work is waiting, and why the dwell column is empty
Why the dwell column is empty
Median days in phase is not shown. 56% of status transitions in this project are zero-elapsed back-fill, so the figure would measure when a status was typed rather than when work moved.
PhaseItemsMedian days
Definition1,666
Ready662
Development467
QA340
SIT & Regression2
Pre-production3
Released to production0
QA passed2,075

Median days in phase is not shown. 56% of status transitions in this project are zero-elapsed back-fill, so the figure would measure when a status was typed rather than when work moved.

377 items blocked, 98 of them from outside the four squadsJira

Blocked items

377

unfinished work on the receiving end of a link

Held by their own squad

274

a sequencing problem inside one team

Held by another squad

5

the only cross-squad constraint recorded

Held from outside the four

98

Integration, Workflow & Decision Engine, or work this page does not report

Who records dependencies, and who does not
Items, not links, and coverage beside the count
Blocked means an unfinished item on the receiving end of a Blocks or Depends link; Relates is narrative association and is excluded. One item held by four tickets is one thing to unblock — an earlier draft counted edges and overstated it by half. A squad recording no links looks unblocked, which is why coverage is a column rather than a note.

377 unfinished items are blocked, by 608 links. No squad blocks another squad’s work, so there is no cross-squad matrix to draw. A further 53 items outside these four squads are waiting on work inside them.

SquadOpen itemsWith any linkLink coverageBlocked
Everyday Banking1,00972472%260
Cards & Lending73751670%90
Payments & Transfers40929672%27
Value Add10500%not recorded

Value Add record no issue links at all, so an empty blocked figure means not recorded rather than not blocked.

InventoryJira

Stories only, and filtering changes nothing above
The figures in the sections above cover the wider population, tasks included. Narrowing this register is display, never derivation: no figure above recomputes, and the count states how many of the whole population are showing so a filtered view cannot be mistaken for the programme.

Showing all 779 user stories.

User stories only. The figures above cover all 5,215 work items in this scope, including the tasks and technical tasks that are not listed here.

KeySummarySquadPhaseStatusSprintReleaseDue
NILE-10148Technical User Story - CASA Details And TransactionsTechnical Epic -CASA View Details and TransactionsEDBDefinitionIn Triage
NILE-10344Dashboard - My CardsCLReadyTo Do18
NILE-10853Submit an Account Transfer or Bill Payment DisputeCurrent Account - Dispute Transaction (MOCK)EDBDefinitionIn TriageR2
NILE-10854View and Update a Transaction Dispute RequestCurrent Account - Dispute Transaction (MOCK)EDBDefinitionIn TriageR2
NILE-10861Credit Card - Apply For a New Card- Upload Identification Document (Supplementary)Credit Cards - Supplementary Card Request (MOCK)CLDefinitionIn TriageR22026-07-16
NILE-10862Credit Card- Apply For a New Card- Card Info Screen (Supplementary)Credit Cards - Supplementary Card Request (MOCK)CLDefinitionIn TriageR22026-07-16
NILE-10863Credit Card- Activate Supplementary Card - Family HubCredit Cards - Supplementary Card Request (MOCK)CLDefinitionIn TriageR22026-07-16
NILE-10865View Periodic Account StatementAccount Statements ManagementEDBDefinitionIn Triage
NILE-10866Request Custom Account Statement Using Date RangeAccount Statements ManagementEDBDefinitionIn Triage
NILE-10867Generate Custom Account Statement Using Predefined PeriodAccount Statements ManagementEDBDefinitionIn Triage
NILE-10868Generate Custom Consolidated Account StatementAccount Statements ManagementEDBDefinitionIn Triage
NILE-10869Receive Push Notification to View Periodic (Monthly) Consolidated StatementAccount Statements ManagementEDBDefinitionIn Triage
NILE-10870Account Statement PDF TemplateAccount Statements ManagementEDBDefinitionIn Triage
NILE-11338Apply (Secured)- Connected Parties DeclarationPersonal Loan (Secured) - Apply - Inputs (MOCK)CLReadyTo DoR22026-08-13
NILE-11339Apply (Secured) - Consent to IScore checkPersonal Loan (Secured) - Apply - Inputs (MOCK)CLReadyTo DoR22026-08-13
NILE-11340Apply (Secured) - Facilities Declaration (IScore Check)Personal Loan (Secured) - Apply - Inputs (MOCK)CLReadyTo DoR22026-08-13
NILE-11341Apply (Secured) - Review Application Details & Submit RequestPersonal Loan (Secured) - Apply - Inputs (MOCK)CLReadyTo DoR22026-08-13
NILE-11342Apply (unsecured) - Loan Details - Duration SelectionPersonal Loan (Unsecured) - Apply - Inputs (MOCK)CLReadyTo DoR22026-08-13
NILE-11343Apply (Secured) - Loan Approval & Final Financing OfferPersonal Loan (Secured) - Apply - Inputs (MOCK)CLReadyTo DoR22026-08-13
NILE-11344Apply (Un-Secured) - Consent to IScore checkPersonal Loan (Unsecured) - Apply - Inputs (MOCK)CLReadyTo DoR22026-08-13
NILE-11345Apply (Un-Secured) - Facilities Declaration (IScore Check)Personal Loan (Unsecured) - Apply - Inputs (MOCK)CLReadyTo DoR22026-08-13
NILE-11346Apply (All Types) - Loan DisbursementPersonal Loan (Secured) - Apply - Inputs (MOCK)CLReadyTo DoR22026-08-13
NILE-11444Apply (Unsecured) - Review Application Details & Submit RequestPersonal Loan (Unsecured) - Apply - Inputs (MOCK)CLReadyTo DoR22026-08-13
NILE-11566Notification Center — View, Filter and Open NotificationsProfile & Settings - Notification Centre (MOCK)VAReadyTo DoR2
NILE-11628Notification Center — Notifications Options MenuProfile & Settings - Notification Centre (MOCK)VAReadyTo DoR2
NILE-1719View Debit Card Landing PageDebit Cards - Card Landing Page (MOCK)CLDevelopmentIn Development18R12026-01-15
NILE-1760Display Debit Card InformationDebit Cards - View Card Details (MOCK)CLDevelopmentIn Development6R12026-01-15
NILE-1761Activate Debit Card - DigitalDebit Cards - Card Activation (MOCK)CLDevelopmentIn Development18R12026-01-15
NILE-1762Activate Physical CardDebit Card - Activate Physical Card (MOCK)CLDevelopmentIn Development6R12026-02-26
NILE-1763View Credit Card Landing PageCredit Cards - View Card Details (MOCK)CLReadyTo Do18R12026-03-06
NILE-1764Change PINDebit Cards - Manage PIN (MOCK)CLDevelopmentIn Development6R12026-01-29
NILE-1765Freeze/ Unfreeze Debit CardDebit Cards - Freeze/Cancel Card (MOCK)CLDevelopmentIn Development18R12026-01-15
NILE-1766Debit Card Limit - Manage Limits - (LCY)Debit Cards - Manage Card Limits in LCY (MOCK)CLDevelopmentIn Development18R12026-03-12
NILE-1767Debit Card Limit - Confirm ChangesDebit Cards - Manage Card Limits in LCY (MOCK)CLDevelopmentIn Development18R12026-03-12
NILE-1871Digital Card IssuanceDebit Cards - Digital Card Issuance (MOCK)CLDevelopmentIn Development6R12026-01-15
NILE-2190Onboarding– Personal Details (Egyptian Nationals – Unhappy Flow)Onboarding - Registration (MOCK)EDBQA passedComplete6R12026-02-12
NILE-2191Origination – Address Details (Egyptian Nationals – Unhappy Flow – Manual Update)Onboarding - Registration (MOCK)EDBQA passedQA test passed8R12026-02-12
NILE-2192Origination – Address Details (Egyptian Nationals – Unhappy Flow – Select From Map Update)Onboarding - Registration (MOCK)EDBQA passedQA test passed12R12026-02-12
NILE-2194Order Physical CardDebit Cards - Physical Card Request (MOCK)CLDevelopmentIn Development6R12026-07-12
NILE-2481Transfers - Between my Accounts - Transfer Details - Same CurrencyTransfers - Between My Accounts LCY (MOCK)P&TDevelopmentIn Development8R12026-02-22
NILE-2483Transfers - Between my accounts - Transfer Review Transfers - Between My Accounts LCY (MOCK)P&TDevelopmentIn Development8R12026-02-22
NILE-2484Transfers - Between My Accounts - Transfer Success -Auto-ApprovedTransfers - Between My Accounts LCY (MOCK)P&TDevelopmentIn Development8R12026-02-22
NILE-2573Savings Account - Open (Account Benefits)EDBQAQA Testing in process18R12026-04-23
NILE-2574Savings Account - Open (Inputs & Success UI)Savings Account - Open savings account (MOCK)EDBQA passedQA test passed14R12026-04-23
NILE-2575Savings Account - View Account DetailsSavings Account - View account details (MOCK)EDBQA passedQA test passed14R12026-04-09
NILE-2576Savings Account - View Account Details (Tab)Savings Account - View account details (MOCK)EDBQA passedQA test passed11R12026-04-09
NILE-2577Savings Account - Share Account DetailsEDBQAQA Testing in process18R12026-04-09
NILE-2578Savings Account - View Account Details (Pledged Funds)EDBQAReady for QA18R12026-05-07
NILE-2579Savings Account - Generate StatementSavings Account - Generate statement (MOCK)EDBQA passedQA test passed12R12026-04-09
NILE-2580Savings Account - View Recent Transactions (Tab)Savings Account - View transactions (MOCK)EDBQA passedQA test passed14R12026-04-14
NILE-2581Savings Account - Search TransactionsSavings Account - View transactions (MOCK)EDBQA passedQA test passed14R12026-04-14
NILE-2582Savings Account - Filter TransactionsEDBQAQA Testing in process18R12026-04-17
NILE-2583Savings Account - Individual TransactionsEDBQAReady for QA18R12026-04-20
NILE-2584Savings Account - CloseEDBQAReady for QA18R12026-04-23
NILE-2585Savings Account - Statuses: Dormant RiskAccounts Lifecycle Management - Flagged Account StatusesEDBDefinitionIn TriageR22026-09-18
NILE-2586Savings Account - Statuses: DormantAccounts Lifecycle Management - Flagged Account StatusesEDBDefinitionIn TriageR22026-09-18
NILE-2587Savings Account - Activate DormantAccounts Lifecycle Management - Flagged Account StatusesEDBDefinitionIn TriageR22026-09-30
NILE-2588Savings Account - Statuses: Blocked / On HoldAccounts Lifecycle Management - Flagged Account StatusesEDBDefinitionIn TriageR22026-09-30
NILE-2589Savings Account - Statuses: Legal ReserveAccounts Lifecycle Management - Flagged Account StatusesEDBDefinitionIn TriageR22026-09-19
NILE-2590Current Account - Details PageEDBQAQA Testing in process18R12026-04-09
NILE-2591Current Account - View Account DetailsEDBQAQA Testing in process18R12026-04-09
NILE-2592Current Account - Share Account DetailsEDBQAQA Testing in process18R12026-04-09
NILE-2593Current Account - Generate StatementCurrent Account - Generate statement (MOCK)EDBQA passedQA test passed15R12026-04-09
NILE-2594Current Account - View Recent TransactionsEDBQAQA Testing in process18R12026-03-22
NILE-2595Current Account - Search/Filter TransactionsEDBQAQA Testing in process18R12026-03-22
NILE-2596Current Account - Filter TransactionsEDBQAQA Testing in process18R12026-03-18
NILE-2597Current Account - Individual TransactionsEDBQAQA Testing in process18R12026-03-21
NILE-2598Current Account - Statuses: Dormant RiskAccounts Lifecycle Management - Flagged Account StatusesEDBDefinitionIn TriageR22026-09-22
NILE-2599Current Account - Statuses: DormantAccounts Lifecycle Management - Flagged Account StatusesEDBDefinitionIn TriageR22026-09-25
NILE-2600Current Account - Activate DormantAccounts Lifecycle Management - Flagged Account StatusesEDBDefinitionIn TriageR22026-09-22
NILE-2601Current Account - Statuses: Blocked / On HoldAccounts Lifecycle Management - Flagged Account StatusesEDBDefinitionIn TriageR22026-09-16
NILE-2602Current Account - Statuses: Legal ReserveAccounts Lifecycle Management - Flagged Account StatusesEDBDefinitionIn TriageR22026-09-20
NILE-2603Customer Profile - Statuses: DormantAccounts Lifecycle Management - Flagged Account StatusesEDBDefinitionIn TriageR22026-09-16
NILE-2604Customer Profile - Statuses: PEP, Sanctions, Blacklist, Security RiskAccounts Lifecycle Management - Flagged Account StatusesEDBDefinitionIn TriageR22026-09-16
NILE-2605Customer Profile - Statuses: Legal ReserveAccounts Lifecycle Management - Flagged Account StatusesEDBDefinitionIn TriageR22026-09-18
NILE-2607Multi-currency Account - Open 1 (Account Benefits)Multicurrency Accounts - Open Account (MOCK)EDBDefinitionIn TriageR12026-07-08
NILE-2608Multi-currency Account - Open 2 (Account Specifications Input)Multicurrency Accounts - Open Account (MOCK)EDBDefinitionIn TriageR12026-07-09
NILE-2609Multi-currency Account - View Account DetailsMulticurrency Accounts - View Account Details (MOCK)EDBDefinitionIn TriageR12026-07-05
NILE-2610Multi-currency Account - View Account Details TabMulticurrency Accounts - View Account Details (MOCK)EDBDefinitionIn TriageR12026-07-08
NILE-2611Multi-currency Account - Share Account DetailsMulticurrency Accounts - View Account Details (MOCK)EDBDefinitionIn TriageR12026-07-11
NILE-2612Multi-currency Account - View Recent TransactionsMulticurrency Accounts - View transactions (MOCK)EDBDefinitionIn TriageR12026-08-13
NILE-2613Multi-currency Account - Search TransactionsMulticurrency Accounts - View transactions (MOCK)EDBDefinitionIn TriageR12026-08-13
NILE-2614Multi-currency Account - Filter TransactionsMulticurrency Accounts - View transactions (MOCK)EDBDefinitionIn TriageR12026-08-20
NILE-2615Multi-currency Account - Individual TransactionsMulticurrency Accounts - View transactions (MOCK)EDBDefinitionIn TriageR12026-08-20
NILE-2616Multi-currency Account - Generate StatementMulticurrency Accounts - Generate statement (MOCK)EDBDefinitionIn TriageR12026-08-28
NILE-2617Multi-currency Account - Add Money 1 (Details)Multicurrency Accounts - Add Currency sub-Account (MOCK)EDBDefinitionIn TriageR12026-07-22
NILE-2618Multi-currency Account - Add Money 2 (Doc Upload)Multicurrency Accounts - Add Currency sub-Account (MOCK)EDBDefinitionIn TriageR12026-07-24
NILE-2619Multi-currency Account - Add Money 3 (Review)Multicurrency Accounts - Add Currency sub-Account (MOCK)EDBDefinitionIn TriageR12026-07-26
NILE-2620Multi-currency Account - Add Money 4 (Success)Multicurrency Accounts - Add Currency sub-Account (MOCK)EDBDefinitionIn TriageR12026-07-29
NILE-2621Multi-currency Account - Send MoneyMulticurrency Accounts - Add Money (including FX) (MOCK)EDBDefinitionIn TriageR12026-08-10
NILE-2622Multi-currency Account - CloseMulticurrency Accounts - Close / Delete Account (MOCK)EDBDefinitionIn TriageR12026-09-08
NILE-2623Break Time Deposit Account - Explore alternative productsEDBQAReady for QA18R12026-05-01
NILE-2624Break Time Deposit Account - Important Notice bottom drawerEDBQAReady for QA18R12026-05-01
NILE-2625Break Time Deposit Account - Breakage TypeEDBQAReady for QA18R12026-05-02
NILE-2626Break Time Deposit Account - Review PageEDBQAReady for QA18R12026-05-02
NILE-2627Break Time Deposit Account - OTP InputEDBQAReady for QA18R12026-05-03
NILE-2628Break Time Deposit Account - Success PageEDBQAReady for QA18R12026-05-06
NILE-2630Break Certificate of Deposit Account - Explore alternative productsEDBQAReady for QA18R12026-05-06
NILE-2631 Break Certificate of Deposit Account - Important Notice bottom drawerEDBQAReady for QA18R12026-05-06
NILE-2632Break Certificate of Deposit Account - Breakage TypeEDBQAReady for QA18R12026-05-06
Showing 100 of 779 matching.

Core Delivery only. “All Board Work” needs the items the task rule turns away, which delivery.csv does not carry.