Payments & Transfers
64 R1 user stories · Payments & Transfers · sprint 18
Search the Command Centre
Jump to a page, or open a Solution Design in Jira.
As of 2026-08-13 · pulled 13 Aug 2026, 23:31 (same day as the last Jira change)
64 R1 user stories in Payments & Transfers.
SummaryJira
Where delivery stands
0% of R1 user stories have passed QA, 58 are in flight, and 0 have reached SIT or beyond. Payments & Transfers carries the most unfinished work between sprints, at 100% of sprint 17 scope.
- “Delivered” means development complete and QA passed — not released. SIT, pre-production and release all come after it.
- Every figure on this page counts user stories only, matching the workflow above. Delivery is executed on the technical tasks beneath a story, and those are not counted here — so this measures scope a business reader recognises, not effort spent.
9% past QA, 0 in production nowJira
The whole programme, then per squad
Definition38
- GRGathering requirements0
- TRIIn Triage38
- RRVReady for review0
- IRVIn review0
- APVApproved0
Ready49
- TODOTo Do49
- REOReopened0
Development126
- DEVIn Development126
- PRVPeer review0
QA77
- RQAReady for QA56
- QATQA Testing in process21
- QAFQA test failed0
Done29
- QAPQA test passed23
- CMPComplete6
SIT & Regression0
- REGIn regression testing0
- RSITReady for SIT0
- DSITDeployed to SIT0
- REGFRegression failed0
- SITFSIT failednever used
Pre-production0
- RPPReady for PreProd0
- DPPDeployed to PreProd0
- ARELApproved for release0
- SCHScheduled for release0
- PPFPreProd failednever used
Production0
- PRODReleased to production0
- MONMonitoring0
- RBKRollback0
No single phase5
- HLDOn hold5
User stories only — 324 of them, across the workflow's 28 statuses, with 1,349 moves between them. Task and Technical Task run a workflow with no test gates and are counted in the bar above but not here. The number in a circle is how many sit there NOW, not how many have passed through. Each chip is that status's own code, unique across the workflow so it can be quoted elsewhere, and coloured by its lifecycle phase. 65 moves went backwards and 63 left the road for a parked, failed or reverted state; every one of those returns to In Triage or To Do, which is why they share one line back.
14 stories released to production, 9% of R1 past QAJira
Progress toward R1, R2 and R3, and the epics under them
0 of 64
0 of 8
0 of 12
In none of these bars, and counted in the page total rather than distributed by guess.
The 10 epics with the most unfinished work, of 14 carrying any. 64 user stories are open across all of them.
An epic’s children here are its stories. The technical tasks beneath them are not counted, so this ranks epics by outstanding scope rather than by work remaining.
| Epic | Squad | Open | Children | QA passed | Furthest phase reached |
|---|---|---|---|---|---|
| NILE-158Transfers - Add/Manage Beneficiaries (MOCK) | P&T | 12 | 12 | 0% | Development |
| NILE-152Transfers - Instant transfers (IPN) (MOCK) | P&T | 11 | 11 | 0% | Development |
| NILE-150Transfers - EZ Bank Internal Transfers (MOCK) | P&T | 6 | 6 | 0% | Development |
| NILE-143Bill Payments - Add/Pay Bills (Post Paid) - (MOCK) | P&T | 5 | 5 | 0% | Ready |
| NILE-151Transfers - Local transfers (ACH) (MOCK) | P&T | 5 | 5 | 0% | Development |
| NILE-157Transfers - Manage Recurring Transfers (MOCK) | P&T | 5 | 5 | 0% | Development |
| NILE-144Bill Payments - Add/Pay Bills (Pre-Paid) - (MOCK) | P&T | 4 | 4 | 0% | Development |
| NILE-145Bill Payments - Manage Bills (MOCK) | P&T | 4 | 4 | 0% | Development |
| NILE-2779Transfers - Between My Accounts LCY (MOCK) | P&T | 4 | 4 | 0% | Development |
| NILE-146Bill Payments - Set Up Auto-bill Payments (MOCK) | P&T | 2 | 2 | 0% | Development |
Sprint deliveryJira
Committed scope and completions
0of 61 in scope
Sprint 18 is still running.
7 of the 16 open R1 activities are behind their own line, and ARB approved for Payments & Transfers is 55 points behind itManual entry
What the plan committed to, and what has arrived
| Kind of work | Release 1 | Release 2 | Release 3 |
|---|---|---|---|
| Elaboration | 712 of 712100% | 348 of 44079% | not started |
| Design gate | 86 of 12370% | not started | not started |
| Build | 589 of 75578% | not started | not started |
| Platform APIs | 0 of 50% | not started | not started |
| Test cases | 4,332 of 6,19470% | not started | not started |
Committed at the start of each sprint against what arrived. Both charts share one scale, so a bar in either stands for the same number of items.
CommittedDelivered
Build
Design gate
2026-09-014 of 6 behind their line
- ARB approvedP&T-557 leftwell behind
- Experience APIsP&T-2421 leftwell behind
- Integration APIsP&T-1512 leftbehind
- Front-end screensP&T-1425 leftbehind
- Test casesP&T0624 lefton its line
- Test casesCL+10465 leftahead
2026-09-263 of 10 behind their line
- Experience APIsEDB-3134 leftwell behind
- ARB approvedCL-1818 leftbehind
- Integration APIsEDB-1635 leftbehind
- Experience APIsCL-34 lefton its line
- Cyber reviewedCL+49 lefton its line
- Front-end screensEDB+618 leftahead
- Integration APIsCL+1317 leftahead
- Test casesEDB+19773 leftahead
- ARB approvedEDB+373 leftahead
- Platform APIs: NICL—5 leftno window
Measured against the plan’s own line. The bar is the share delivered; the tick is the share of that activity's own window that has gone, from its first committed sprint to its revised target. Both come from the plan. The gap between them is the number. The only judgement is where it becomes a word: behind past 5 points, well behind past 20.
| Activity | Everyday Banking | Cards & Lending | Payments & Transfers | Value Add |
|---|---|---|---|---|
| Elaboration | ||||
| Regulatory review | 143 of 143 100% | 125 of 125 100% | 75 of 75 100% | 13 of 13 100% |
| UI/UX and customer journey | 29 of 29 100% | 31 of 31 100% | 15 of 15 100% | 3 of 3 100% |
| User stories | 114 of 114 100% | 94 of 94 100% | 60 of 60 100% | 10 of 10 100% |
| Design gate | ||||
| ARB approved | 8 of 11 73% | 4 of 22 18% | 1 of 8 13% | — |
| Cyber reviewed | 11 of 11 100% | 13 of 22 59% | 8 of 8 100% | — |
| Solution design finalised | 11 of 11 100% | 22 of 22 100% | 8 of 8 100% | — |
| Build | ||||
| Experience APIs | 37 of 71 52% | 18 of 22 82% | 42 of 63 67% | — |
| Front-end screens | 150 of 168 89% | 144 of 144 100% | 84 of 109 77% | 17 of 17 100% |
| Integration APIs | 27 of 62 44% | 47 of 64 73% | 23 of 35 66% | — |
| Platform APIs | ||||
| Platform APIs: NI | · | 0 of 5 0% | · | — |
| Platform APIs: Payment Hub | · | · | — | · |
| Platform APIs: T24 | — | · | · | — |
| Platform APIs: TPH | · | · | · | — |
| Test cases | ||||
| Test cases | 1,528 of 2,301 66% | 1,519 of 1,984 77% | 1,285 of 1,909 67% | — |
| Test cases including the deep layer | — | — | — | — |
Squad and activity totals, not individual artefacts. The source is an aggregate grid, so this section cannot be drilled into.
PredictabilityJira
Does committed scope finish when committed
100%61 of 61 in sprint 17 scope
- S12
- S13
- S14
- S15
- S16
- S17
0%0 of 0 completed with a due date
Not enough completed sprints yet to show a trend.
0 of 0 completed items carry a due date. The line is each sprint's own completions, the figure above is every completed item to date.
10% of work that reached Development came back to itJira
How work moves, where it stops, what cannot be ranked
0%0 of 52 that reached Development
Waiting on declared thresholds, not on build time. Solution Design’s 14 and 30-day bands are that page’s, not this one’s.
| Phase | Items | Median days |
|---|---|---|
| Definition | 6 | — |
| Ready | 6 | — |
| Development | 52 | — |
| QA | 0 | — |
| SIT & Regression | 0 | — |
| Pre-production | 0 | — |
| Released to production | 0 | — |
| QA passed | 0 | — |
Median days in phase is not shown. 56% of status transitions in this project are zero-elapsed back-fill, so the figure would measure when a status was typed rather than when work moved.
45 stories blocked, 21 of them from outside the four squadsJira
What is blocked, and by whom
2
unfinished stories on the receiving end of a link
0
a sequencing problem inside one team
0
the only cross-squad constraint recorded
2
Integration, Workflow & Decision Engine, or work this page does not report
2 unfinished user stories are blocked, by 6 links. No squad blocks another squad’s work, so there is no cross-squad matrix to draw. A further 2 work items outside these four squads are waiting on work inside them.
| Squad | Open stories | With any link | Link coverage | Blocked |
|---|---|---|---|---|
| Payments & Transfers | 64 | 63 | 98% | 2 |
InventoryJira
Every user story this page counts
Showing all 64 user stories.
| Key | Summary | Squad | Phase | Status | Sprint | Release | Due | |
|---|---|---|---|---|---|---|---|---|
| NILE-2481 | Transfers - Between my Accounts - Transfer Details - Same CurrencyTransfers - Between My Accounts LCY (MOCK) | P&T | Development | In Development | 8 | R1 | 2026-02-22 | |
| NILE-2483 | Transfers - Between my accounts - Transfer Review Transfers - Between My Accounts LCY (MOCK) | P&T | Development | In Development | 8 | R1 | 2026-02-22 | |
| NILE-2484 | Transfers - Between My Accounts - Transfer Success -Auto-ApprovedTransfers - Between My Accounts LCY (MOCK) | P&T | Development | In Development | 8 | R1 | 2026-02-22 | |
| NILE-2703 | Transfers - EZ Bank Internal Transfers - Beneficiary SelectTransfers - EZ Bank Internal Transfers (MOCK) | P&T | Development | In Development | 8 | R1 | 2026-03-08 | |
| NILE-2704 | Transfers - EZ Bank Internal Transfers - Beneficiary CreationTransfers - EZ Bank Internal Transfers (MOCK) | P&T | Development | In Development | 8 | R1 | 2026-03-08 | |
| NILE-2705 | Transfers - Payments & Transfers DashboardTransfers - Payments & Transfers Dashboard (MOCK) | P&T | Development | In Development | 8 | R1 | 2026-02-12 | |
| NILE-2706 | Transfers - IPN - Beneficiary SelectionTransfers - Instant transfers (IPN) (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-04-23 | |
| NILE-2709 | Transfers - IPN - Beneficiary Creation- Mobile NumberTransfers - Instant transfers (IPN) (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-04-23 | |
| NILE-2710 | Transfers - IPN- Beneficiary Creation- IPATransfers - Instant transfers (IPN) (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-04-23 | |
| NILE-2711 | Transfers - IPN - Beneficiary Creation - Account NumberTransfers - Instant transfers (IPN) (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-04-23 | |
| NILE-2712 | Transfers - IPN - Beneficiary Creation - IBAN Transfers - Instant transfers (IPN) (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-04-23 | |
| NILE-2713 | Transfers - IPN - Beneficiary Creation - Card NumberTransfers - Instant transfers (IPN) (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-04-23 | |
| NILE-2714 | Transfers - IPN - Beneficiary Creation - Wallet NumberTransfers - Instant transfers (IPN) (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-04-23 | |
| NILE-2715 | Transfers - IPN -Transfer Details Transfers - Instant transfers (IPN) (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-04-23 | |
| NILE-2716 | Transfers - IPN - Transfer ReviewTransfers - Instant transfers (IPN) (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-04-23 | |
| NILE-2717 | Transfers - IPN - Transfer SuccessTransfers - Instant transfers (IPN) (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-04-23 | |
| NILE-2718 | Transfers - ACH - Beneficiary SelectionTransfers - Local transfers (ACH) (MOCK) | P&T | Development | In Development | 7 | R1 | 2026-04-23 | |
| NILE-2719 | Transfers - ACH - Beneficiary CreationTransfers - Local transfers (ACH) (MOCK) | P&T | Development | In Development | 7 | R1 | 2026-04-23 | |
| NILE-2720 | Transfers - ACH - Transfer DetailsTransfers - Local transfers (ACH) (MOCK) | P&T | Development | In Development | 7 | R1 | 2026-04-23 | |
| NILE-2721 | Transfers - ACH - Transfer ReviewTransfers - Local transfers (ACH) (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-04-23 | |
| NILE-2722 | Transfers - ACH - Transfer SuccessTransfers - Local transfers (ACH) (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-04-23 | |
| NILE-2723 | Manage Beneficiaries - Manage Beneficiary Landing Page (Full List)Transfers - Add/Manage Beneficiaries (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-07 | |
| NILE-2724 | Manage Beneficiaries - Add BeneficiaryTransfers - Add/Manage Beneficiaries (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-07 | |
| NILE-2725 | Manage Beneficiaries - Add Beneficiary Success ScreenTransfers - Add/Manage Beneficiaries (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-07 | |
| NILE-2726 | Manage Beneficiaries - Manage Beneficiary - View DetailsTransfers - Add/Manage Beneficiaries (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-07 | |
| NILE-2739 | Bill Payments- Make a Payment Landing PageBill Payments - Select Bill Category (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-06-04 | |
| NILE-2740 | Bill Payments - Category & Provider SelectionBill Payments - Select Bill Category (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-06-04 | |
| NILE-2741 | Bill Payments- Add a New Bill- Bill details (post-paid)Bill Payments - Add/Pay Bills (Post Paid) - (MOCK) | P&T | Ready | To Do | 16 | R1 | 2026-06-04 | |
| NILE-2742 | Bill Payments- Add a New Bill- Review page (Post-Paid)Bill Payments - Add/Pay Bills (Post Paid) - (MOCK) | P&T | Ready | To Do | 16 | R1 | 2026-06-04 | |
| NILE-2743 | Bill Payments- Add A New Bill- Success Page (Post-Paid)Bill Payments - Add/Pay Bills (Post Paid) - (MOCK) | P&T | Ready | To Do | 16 | R1 | 2026-06-04 | |
| NILE-2744 | Bill Payments - Manage Bill - Details PageBill Payments - Manage Bills (MOCK) | P&T | Definition | In Triage | 16 | R1 | 2026-06-18 | |
| NILE-2745 | Bill Payments- Manage Bill - Pay Favorite BillBill Payments - Manage Bills (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-06-18 | |
| NILE-2746 | Bill Payments- Manage Bill - Delete BillBill Payments - Manage Bills (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-06-18 | |
| NILE-2747 | Bill Payments - Add a New Bill - Bill Inquiry (Pre-Paid)Bill Payments - Add/Pay Bills (Pre-Paid) - (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-06-04 | |
| NILE-2748 | Bill Payments - Add a New Bill - Bill Details (Pre-Paid)Bill Payments - Add/Pay Bills (Pre-Paid) - (MOCK) | P&T | Ready | To Do | 16 | R1 | 2026-06-04 | |
| NILE-2749 | Bill Payments- Add a New Bill - Review Page (Pre-Paid)Bill Payments - Add/Pay Bills (Pre-Paid) - (MOCK) | P&T | Ready | To Do | 16 | R1 | 2026-06-04 | |
| NILE-2750 | Bill Payments - Add a New Bill - Success Page (Pre-paid)Bill Payments - Add/Pay Bills (Pre-Paid) - (MOCK) | P&T | Ready | To Do | 16 | R1 | 2026-06-04 | |
| NILE-3318 | Transfers - Between my Accounts - Transfer Success - View ReceiptTransfers - Between My Accounts LCY (MOCK) | P&T | Definition | On hold | 8 | R1 | 2026-02-22 | |
| NILE-3325 | Transfer Success NotificationTransfers - EZ Bank Internal Transfers (MOCK) | P&T | Definition | In Triage | — | R1 | 2026-07-26 | |
| NILE-3921 | Transfers - EZ Bank Internal Transfers - Transfer Details ScreenTransfers - EZ Bank Internal Transfers (MOCK) | P&T | Development | In Development | 8 | R1 | 2026-03-08 | |
| NILE-3922 | Transfers - EZ Bank Internal Transfers - Review ScreenTransfers - EZ Bank Internal Transfers (MOCK) | P&T | Development | In Development | 8 | R1 | 2026-03-08 | |
| NILE-3923 | Transfers - EZ Bank Internal Transfers - Transfer SuccessTransfers - EZ Bank Internal Transfers (MOCK) | P&T | Development | In Development | 8 | R1 | 2026-03-22 | |
| NILE-4254 | Bill Payments - Manage Bill - Edit BillBill Payments - Manage Bills (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-06-18 | |
| NILE-4255 | Setup Auto-Bill Payments - Enable Auto-PaymentBill Payments - Set Up Auto-bill Payments (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-07-02 | |
| NILE-4257 | Set Up Auto-Bill Payment - Max Limit PaymentBill Payments - Set Up Auto-bill Payments (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-07-02 | |
| NILE-4258 | Manage Beneficiaries - Search BeneficiaryTransfers - Add/Manage Beneficiaries (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-07 | |
| NILE-4259 | Manage Beneficiaries - Delete BeneficiaryTransfers - Add/Manage Beneficiaries (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-07 | |
| NILE-4261 | Manage Recurring Payments - Manage Recurring PaymentTransfers - Manage Recurring Transfers (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-21 | |
| NILE-4262 | Setup Recurring Payments - Add Recurring PaymentTransfers - Setup Recurring Transfers (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-21 | |
| NILE-4263 | Setup Recurring Payments - Add Recurring Payment (Success Page)Transfers - Setup Recurring Transfers (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-21 | |
| NILE-4264 | Manage Recurring Payments - Pause Recurring PaymentTransfers - Manage Recurring Transfers (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-21 | |
| NILE-4265 | Manage Recurring Payments - Edit Recurring PaymentTransfers - Manage Recurring Transfers (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-21 | |
| NILE-4266 | Manage Recurring Payments - Reactivate Recurring PaymentTransfers - Manage Recurring Transfers (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-21 | |
| NILE-4267 | Manage Recurring Payments - Cancel Recurring PaymentTransfers - Manage Recurring Transfers (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-21 | |
| NILE-4268 | AML Transaction Screening - Trnx ScreeningTransfers - AML transaction screening (MOCK) | P&T | Definition | In Triage | — | R1 | 2026-05-21 | |
| NILE-6760 | Transfers - IPN - Method SelectionTransfers - Instant transfers (IPN) (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-04-23 | |
| NILE-7611 | Bill Payments- Add a new bill- Bill Inquiry (post-paid)Bill Payments - Add/Pay Bills (Post Paid) - (MOCK) | P&T | Definition | In Triage | — | R1 | 2026-06-04 | |
| NILE-8168 | Bill Payments- Add a New Bill- Bill details (post-paid) - Multiple DuesBill Payments - Add/Pay Bills (Post Paid) - (MOCK) | P&T | Definition | In Triage | 16 | R1 | 2026-06-04 | |
| NILE-9301 | Manage Beneficiaries - Add Beneficiary - Within EZ BankTransfers - Add/Manage Beneficiaries (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-07 | |
| NILE-9302 | Manage Beneficiaries - Add Beneficiary - ACHTransfers - Add/Manage Beneficiaries (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-07 | |
| NILE-9303 | Manage Beneficiaries - Add Beneficiary - IPNTransfers - Add/Manage Beneficiaries (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-07 | |
| NILE-9304 | Manage Beneficiaries - Manage Beneficiary - View Details - Within EZ BankTransfers - Add/Manage Beneficiaries (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-07 | |
| NILE-9305 | Manage Beneficiaries - Manage Beneficiary - View Details - ACHTransfers - Add/Manage Beneficiaries (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-07 | |
| NILE-9306 | Manage Beneficiaries - Manage Beneficiary - View Details - IPNTransfers - Add/Manage Beneficiaries (MOCK) | P&T | Development | In Development | 16 | R1 | 2026-05-07 |
User stories in Core Delivery, the same population the workflow above is drawn from. Tasks and technical tasks run a workflow with no test gates and are not counted anywhere on this page. “All Board Work” needs the items the task rule turns away, which delivery.csv does not carry.