Everyday Banking
140 R1 user stories · Everyday Banking · sprint 18
Search the Command Centre
Jump to a page, or open a Solution Design in Jira.
As of 2026-08-13 · pulled 13 Aug 2026, 23:31 (same day as the last Jira change)
140 R1 user stories in Everyday Banking.
SummaryJira
Where delivery stands
21% of R1 user stories have passed QA, 86 are in flight, and 0 have reached SIT or beyond. Everyday Banking carries the most unfinished work between sprints, at 100% of sprint 17 scope.
- “Delivered” means development complete and QA passed. 14 of these stories have since been released to production; the rest are not released — SIT, pre-production and release all come after it.
- Every figure on this page counts user stories only, matching the workflow above. Delivery is executed on the technical tasks beneath a story, and those are not counted here — so this measures scope a business reader recognises, not effort spent.
9% past QA, 0 in production nowJira
The whole programme, then per squad
Definition38
- GRGathering requirements0
- TRIIn Triage38
- RRVReady for review0
- IRVIn review0
- APVApproved0
Ready49
- TODOTo Do49
- REOReopened0
Development126
- DEVIn Development126
- PRVPeer review0
QA77
- RQAReady for QA56
- QATQA Testing in process21
- QAFQA test failed0
Done29
- QAPQA test passed23
- CMPComplete6
SIT & Regression0
- REGIn regression testing0
- RSITReady for SIT0
- DSITDeployed to SIT0
- REGFRegression failed0
- SITFSIT failednever used
Pre-production0
- RPPReady for PreProd0
- DPPDeployed to PreProd0
- ARELApproved for release0
- SCHScheduled for release0
- PPFPreProd failednever used
Production0
- PRODReleased to production0
- MONMonitoring0
- RBKRollback0
No single phase5
- HLDOn hold5
User stories only — 324 of them, across the workflow's 28 statuses, with 1,349 moves between them. Task and Technical Task run a workflow with no test gates and are counted in the bar above but not here. The number in a circle is how many sit there NOW, not how many have passed through. Each chip is that status's own code, unique across the workflow so it can be quoted elsewhere, and coloured by its lifecycle phase. 65 moves went backwards and 63 left the road for a parked, failed or reverted state; every one of those returns to In Triage or To Do, which is why they share one line back.
14 stories released to production, 9% of R1 past QAJira
Progress toward R1, R2 and R3, and the epics under them
29 of 140
0 of 42
0 of 56
In none of these bars, and counted in the page total rather than distributed by guess.
The 10 epics with the most unfinished work, of 26 carrying any. 32 user stories are open across all of them.
An epic’s children here are its stories. The technical tasks beneath them are not counted, so this ranks epics by outstanding scope rather than by work remaining.
| Epic | Squad | Open | Children | QA passed | Furthest phase reached |
|---|---|---|---|---|---|
| NILE-52Login - Forgot/Reset Credentials (MOCK) | EDB | 4 | 5 | 20% | QA passed |
| NILE-62Multicurrency Accounts - Add Currency sub-Account (MOCK) | EDB | 4 | 4 | 0% | Definition |
| NILE-64Multicurrency Accounts - View transactions (MOCK) | EDB | 4 | 4 | 0% | Definition |
| NILE-44Onboarding - Registration (MOCK) | EDB | 3 | 13 | 77% | QA passed |
| NILE-2243Multicurrency Accounts - View Account Details (MOCK) | EDB | 3 | 3 | 0% | Definition |
| NILE-1241Onboarding - Assisted Enrollment (Mtablet) | EDB | 2 | 2 | 0% | Definition |
| NILE-61Multicurrency Accounts - Open Account (MOCK) | EDB | 2 | 2 | 0% | Definition |
| NILE-196Profile & Settings - View Policies (MOCK) | EDB | 1 | 1 | 0% | Definition |
| NILE-197Profile & Settings - Landing Page | EDB | 1 | 1 | 0% | Definition |
| NILE-2252Multicurrency Accounts - Close / Delete Account (MOCK) | EDB | 1 | 1 | 0% | Definition |
Sprint deliveryJira
Committed scope and completions
0of 78 in scope
Sprint 18 is still running.
7 of the 16 open R1 activities are behind their own line, and ARB approved for Payments & Transfers is 55 points behind itManual entry
What the plan committed to, and what has arrived
| Kind of work | Release 1 | Release 2 | Release 3 |
|---|---|---|---|
| Elaboration | 712 of 712100% | 348 of 44079% | not started |
| Design gate | 86 of 12370% | not started | not started |
| Build | 589 of 75578% | not started | not started |
| Platform APIs | 0 of 50% | not started | not started |
| Test cases | 4,332 of 6,19470% | not started | not started |
Committed at the start of each sprint against what arrived. Both charts share one scale, so a bar in either stands for the same number of items.
CommittedDelivered
Build
Design gate
2026-09-014 of 6 behind their line
- ARB approvedP&T-557 leftwell behind
- Experience APIsP&T-2421 leftwell behind
- Integration APIsP&T-1512 leftbehind
- Front-end screensP&T-1425 leftbehind
- Test casesP&T0624 lefton its line
- Test casesCL+10465 leftahead
2026-09-263 of 10 behind their line
- Experience APIsEDB-3134 leftwell behind
- ARB approvedCL-1818 leftbehind
- Integration APIsEDB-1635 leftbehind
- Experience APIsCL-34 lefton its line
- Cyber reviewedCL+49 lefton its line
- Front-end screensEDB+618 leftahead
- Integration APIsCL+1317 leftahead
- Test casesEDB+19773 leftahead
- ARB approvedEDB+373 leftahead
- Platform APIs: NICL—5 leftno window
Measured against the plan’s own line. The bar is the share delivered; the tick is the share of that activity's own window that has gone, from its first committed sprint to its revised target. Both come from the plan. The gap between them is the number. The only judgement is where it becomes a word: behind past 5 points, well behind past 20.
| Activity | Everyday Banking | Cards & Lending | Payments & Transfers | Value Add |
|---|---|---|---|---|
| Elaboration | ||||
| Regulatory review | 143 of 143 100% | 125 of 125 100% | 75 of 75 100% | 13 of 13 100% |
| UI/UX and customer journey | 29 of 29 100% | 31 of 31 100% | 15 of 15 100% | 3 of 3 100% |
| User stories | 114 of 114 100% | 94 of 94 100% | 60 of 60 100% | 10 of 10 100% |
| Design gate | ||||
| ARB approved | 8 of 11 73% | 4 of 22 18% | 1 of 8 13% | — |
| Cyber reviewed | 11 of 11 100% | 13 of 22 59% | 8 of 8 100% | — |
| Solution design finalised | 11 of 11 100% | 22 of 22 100% | 8 of 8 100% | — |
| Build | ||||
| Experience APIs | 37 of 71 52% | 18 of 22 82% | 42 of 63 67% | — |
| Front-end screens | 150 of 168 89% | 144 of 144 100% | 84 of 109 77% | 17 of 17 100% |
| Integration APIs | 27 of 62 44% | 47 of 64 73% | 23 of 35 66% | — |
| Platform APIs | ||||
| Platform APIs: NI | · | 0 of 5 0% | · | — |
| Platform APIs: Payment Hub | · | · | — | · |
| Platform APIs: T24 | — | · | · | — |
| Platform APIs: TPH | · | · | · | — |
| Test cases | ||||
| Test cases | 1,528 of 2,301 66% | 1,519 of 1,984 77% | 1,285 of 1,909 67% | — |
| Test cases including the deep layer | — | — | — | — |
Squad and activity totals, not individual artefacts. The source is an aggregate grid, so this section cannot be drilled into.
PredictabilityJira
Does committed scope finish when committed
100%78 of 78 in sprint 17 scope
- S12
- S13
- S14
- S15
- S16
- S17
0%0 of 29 completed with a due date
- S12
- S13
- S14
- S15
- S16
- S17
29 of 29 completed items carry a due date. The line is each sprint's own completions, the figure above is every completed item to date.
10% of work that reached Development came back to itJira
How work moves, where it stops, what cannot be ranked
14%15 of 108 that reached Development
Waiting on declared thresholds, not on build time. Solution Design’s 14 and 30-day bands are that page’s, not this one’s.
| Phase | Items | Median days |
|---|---|---|
| Definition | 25 | — |
| Ready | 7 | — |
| Development | 2 | — |
| QA | 77 | — |
| SIT & Regression | 0 | — |
| Pre-production | 0 | — |
| Released to production | 0 | — |
| QA passed | 29 | — |
Median days in phase is not shown. 56% of status transitions in this project are zero-elapsed back-fill, so the figure would measure when a status was typed rather than when work moved.
45 stories blocked, 21 of them from outside the four squadsJira
What is blocked, and by whom
12
unfinished stories on the receiving end of a link
2
a sequencing problem inside one team
0
the only cross-squad constraint recorded
10
Integration, Workflow & Decision Engine, or work this page does not report
12 unfinished user stories are blocked, by 40 links. No squad blocks another squad’s work, so there is no cross-squad matrix to draw. A further 25 work items outside these four squads are waiting on work inside them.
| Squad | Open stories | With any link | Link coverage | Blocked |
|---|---|---|---|---|
| Everyday Banking | 140 | 116 | 83% | 12 |
InventoryJira
Every user story this page counts
Showing all 140 user stories.
| Key | Summary | Squad | Phase | Status | Sprint | Release | Due | |
|---|---|---|---|---|---|---|---|---|
| NILE-2190 | Onboarding– Personal Details (Egyptian Nationals – Unhappy Flow)Onboarding - Registration (MOCK) | EDB | QA passed | Complete | 6 | R1 | 2026-02-12 | |
| NILE-2191 | Origination – Address Details (Egyptian Nationals – Unhappy Flow – Manual Update)Onboarding - Registration (MOCK) | EDB | QA passed | QA test passed | 8 | R1 | 2026-02-12 | |
| NILE-2192 | Origination – Address Details (Egyptian Nationals – Unhappy Flow – Select From Map Update)Onboarding - Registration (MOCK) | EDB | QA passed | QA test passed | 12 | R1 | 2026-02-12 | |
| NILE-2573 | Savings Account - Open (Account Benefits) | EDB | QA | QA Testing in process | 18 | R1 | 2026-04-23 | |
| NILE-2574 | Savings Account - Open (Inputs & Success UI)Savings Account - Open savings account (MOCK) | EDB | QA passed | QA test passed | 14 | R1 | 2026-04-23 | |
| NILE-2575 | Savings Account - View Account DetailsSavings Account - View account details (MOCK) | EDB | QA passed | QA test passed | 14 | R1 | 2026-04-09 | |
| NILE-2576 | Savings Account - View Account Details (Tab)Savings Account - View account details (MOCK) | EDB | QA passed | QA test passed | 11 | R1 | 2026-04-09 | |
| NILE-2577 | Savings Account - Share Account Details | EDB | QA | QA Testing in process | 18 | R1 | 2026-04-09 | |
| NILE-2578 | Savings Account - View Account Details (Pledged Funds) | EDB | QA | Ready for QA | 18 | R1 | 2026-05-07 | |
| NILE-2579 | Savings Account - Generate StatementSavings Account - Generate statement (MOCK) | EDB | QA passed | QA test passed | 12 | R1 | 2026-04-09 | |
| NILE-2580 | Savings Account - View Recent Transactions (Tab)Savings Account - View transactions (MOCK) | EDB | QA passed | QA test passed | 14 | R1 | 2026-04-14 | |
| NILE-2581 | Savings Account - Search TransactionsSavings Account - View transactions (MOCK) | EDB | QA passed | QA test passed | 14 | R1 | 2026-04-14 | |
| NILE-2582 | Savings Account - Filter Transactions | EDB | QA | QA Testing in process | 18 | R1 | 2026-04-17 | |
| NILE-2583 | Savings Account - Individual Transactions | EDB | QA | Ready for QA | 18 | R1 | 2026-04-20 | |
| NILE-2584 | Savings Account - Close | EDB | QA | Ready for QA | 18 | R1 | 2026-04-23 | |
| NILE-2590 | Current Account - Details Page | EDB | QA | QA Testing in process | 18 | R1 | 2026-04-09 | |
| NILE-2591 | Current Account - View Account Details | EDB | QA | QA Testing in process | 18 | R1 | 2026-04-09 | |
| NILE-2592 | Current Account - Share Account Details | EDB | QA | QA Testing in process | 18 | R1 | 2026-04-09 | |
| NILE-2593 | Current Account - Generate StatementCurrent Account - Generate statement (MOCK) | EDB | QA passed | QA test passed | 15 | R1 | 2026-04-09 | |
| NILE-2594 | Current Account - View Recent Transactions | EDB | QA | QA Testing in process | 18 | R1 | 2026-03-22 | |
| NILE-2595 | Current Account - Search/Filter Transactions | EDB | QA | QA Testing in process | 18 | R1 | 2026-03-22 | |
| NILE-2596 | Current Account - Filter Transactions | EDB | QA | QA Testing in process | 18 | R1 | 2026-03-18 | |
| NILE-2597 | Current Account - Individual Transactions | EDB | QA | QA Testing in process | 18 | R1 | 2026-03-21 | |
| NILE-2607 | Multi-currency Account - Open 1 (Account Benefits)Multicurrency Accounts - Open Account (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-07-08 | |
| NILE-2608 | Multi-currency Account - Open 2 (Account Specifications Input)Multicurrency Accounts - Open Account (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-07-09 | |
| NILE-2609 | Multi-currency Account - View Account DetailsMulticurrency Accounts - View Account Details (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-07-05 | |
| NILE-2610 | Multi-currency Account - View Account Details TabMulticurrency Accounts - View Account Details (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-07-08 | |
| NILE-2611 | Multi-currency Account - Share Account DetailsMulticurrency Accounts - View Account Details (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-07-11 | |
| NILE-2612 | Multi-currency Account - View Recent TransactionsMulticurrency Accounts - View transactions (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-08-13 | |
| NILE-2613 | Multi-currency Account - Search TransactionsMulticurrency Accounts - View transactions (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-08-13 | |
| NILE-2614 | Multi-currency Account - Filter TransactionsMulticurrency Accounts - View transactions (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-08-20 | |
| NILE-2615 | Multi-currency Account - Individual TransactionsMulticurrency Accounts - View transactions (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-08-20 | |
| NILE-2616 | Multi-currency Account - Generate StatementMulticurrency Accounts - Generate statement (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-08-28 | |
| NILE-2617 | Multi-currency Account - Add Money 1 (Details)Multicurrency Accounts - Add Currency sub-Account (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-07-22 | |
| NILE-2618 | Multi-currency Account - Add Money 2 (Doc Upload)Multicurrency Accounts - Add Currency sub-Account (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-07-24 | |
| NILE-2619 | Multi-currency Account - Add Money 3 (Review)Multicurrency Accounts - Add Currency sub-Account (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-07-26 | |
| NILE-2620 | Multi-currency Account - Add Money 4 (Success)Multicurrency Accounts - Add Currency sub-Account (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-07-29 | |
| NILE-2621 | Multi-currency Account - Send MoneyMulticurrency Accounts - Add Money (including FX) (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-08-10 | |
| NILE-2622 | Multi-currency Account - CloseMulticurrency Accounts - Close / Delete Account (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-09-08 | |
| NILE-2623 | Break Time Deposit Account - Explore alternative products | EDB | QA | Ready for QA | 18 | R1 | 2026-05-01 | |
| NILE-2624 | Break Time Deposit Account - Important Notice bottom drawer | EDB | QA | Ready for QA | 18 | R1 | 2026-05-01 | |
| NILE-2625 | Break Time Deposit Account - Breakage Type | EDB | QA | Ready for QA | 18 | R1 | 2026-05-02 | |
| NILE-2626 | Break Time Deposit Account - Review Page | EDB | QA | Ready for QA | 18 | R1 | 2026-05-02 | |
| NILE-2627 | Break Time Deposit Account - OTP Input | EDB | QA | Ready for QA | 18 | R1 | 2026-05-03 | |
| NILE-2628 | Break Time Deposit Account - Success Page | EDB | QA | Ready for QA | 18 | R1 | 2026-05-06 | |
| NILE-2630 | Break Certificate of Deposit Account - Explore alternative products | EDB | QA | Ready for QA | 18 | R1 | 2026-05-06 | |
| NILE-2631 | Break Certificate of Deposit Account - Important Notice bottom drawer | EDB | QA | Ready for QA | 18 | R1 | 2026-05-06 | |
| NILE-2632 | Break Certificate of Deposit Account - Breakage Type | EDB | QA | Ready for QA | 18 | R1 | 2026-05-06 | |
| NILE-2633 | Break Certificate of Deposit Account - Review Page | EDB | QA | Ready for QA | 18 | R1 | 2026-05-06 | |
| NILE-2634 | Break Certificate of Deposit Account - OTP Input | EDB | QA | Ready for QA | 18 | R1 | 2026-05-06 | |
| NILE-2635 | Break Certificate of Deposit Account - Success Page | EDB | QA | Ready for QA | 18 | R1 | 2026-05-06 | |
| NILE-2636 | Open Time Deposit Account - Account Benefits | EDB | QA | Ready for QA | 18 | R1 | 2026-05-07 | |
| NILE-2637 | Open Time Deposit Account - Account Specifications | EDB | QA | Ready for QA | 18 | R1 | 2026-05-07 | |
| NILE-2638 | Open Time Deposit Account - Interest & Renewal | EDB | QA | Ready for QA | 18 | R1 | 2026-05-07 | |
| NILE-2639 | Open Time Deposit Account - Review Page | EDB | QA | Ready for QA | 18 | R1 | 2026-05-07 | |
| NILE-2640 | Open Time Deposit Account - Success Page | EDB | QA | Ready for QA | 18 | R1 | 2026-05-07 | |
| NILE-2641 | Open Certificate of Deposit Account - Accounts Benefits | EDB | QA | QA Testing in process | 18 | R1 | 2026-05-07 | |
| NILE-2642 | Open Certificate of Deposit Account - Account Specifications | EDB | QA | Ready for QA | 18 | R1 | 2026-05-07 | |
| NILE-2643 | Open Certificate of Deposit Account - Interest & Renewal | EDB | QA | Ready for QA | 18 | R1 | 2026-05-07 | |
| NILE-2644 | Open Certificate of Deposit Account - Review Page | EDB | QA | Ready for QA | 18 | R1 | 2026-05-07 | |
| NILE-2645 | Open Certificate of Deposit Account - Success Page | EDB | QA | Ready for QA | 18 | R1 | 2026-05-07 | |
| NILE-2646 | Certificate of Deposit Generate Statement | EDB | QA | Ready for QA | 18 | R1 | 2026-05-07 | |
| NILE-2647 | Certificate of Deposit View Account Details | EDB | QA | Ready for QA | 18 | R1 | 2026-06-30 | |
| NILE-2648 | Time Deposit View Account Details | EDB | QA | Ready for QA | 18 | R1 | 2026-05-07 | |
| NILE-2649 | Time Deposit View Account Details Tab | EDB | QA | Ready for QA | 18 | R1 | 2026-05-07 | |
| NILE-2652 | Certificate of Deposit Account View Recent Transactions | EDB | QA | Ready for QA | 18 | R1 | 2026-06-15 | |
| NILE-2653 | Certificate of Deposit Account Search Transactions | EDB | QA | Ready for QA | 18 | R1 | 2026-06-17 | |
| NILE-2654 | Certificate of Deposit Account Filter Transactions | EDB | QA | Ready for QA | 18 | R1 | 2026-06-19 | |
| NILE-2655 | Certificate of Deposit Account Individual Transactions | EDB | QA | Ready for QA | 18 | R1 | 2026-06-21 | |
| NILE-2656 | Time Deposit Account View Recent Transactions | EDB | QA | Ready for QA | 18 | R1 | 2026-06-23 | |
| NILE-2657 | Time Deposit Account Search Transactions | EDB | QA | Ready for QA | 18 | R1 | 2026-06-24 | |
| NILE-2658 | Time Deposit Account Filter Transactions | EDB | QA | Ready for QA | 18 | R1 | 2026-06-27 | |
| NILE-2659 | Time Deposit Account Individual Transactions | EDB | QA | Ready for QA | 18 | R1 | 2026-06-29 | |
| NILE-2661 | Origination- Account Opening – Email Notification | EDB | QA | Ready for QA | 18 | R1 | 2026-03-12 | |
| NILE-2662 | Origination- Account Opening Success Page | EDB | QA | QA Testing in process | 18 | R1 | 2026-03-12 | |
| NILE-2663 | Origination - Missing Documents (KYC)Onboarding - AML / Enhanced Due Diligence (System Integration) | EDB | QA | QA Testing in process | 13 | R1 | 2026-03-12 | |
| NILE-2664 | Origination - AML Adjudication (Bank)Onboarding - AML / Enhanced Due Diligence (MOCK) | EDB | QA passed | QA test passed | 12 | R1 | 2026-03-12 | |
| NILE-2665 | Origination - Enhanced Due Diligence | EDB | QA | QA Testing in process | 18 | R1 | 2026-03-12 | |
| NILE-2771 | Origination – Financial Information (Egyptian Nationals – Happy Flow):Onboarding - Registration (MOCK) | EDB | QA passed | Complete | 7 | R1 | 2026-02-12 | |
| NILE-2772 | Origination – Financial Information (Egyptian Nationals – Unhappy Flow):Onboarding - Registration (MOCK) | EDB | QA passed | QA test passed | 12 | R1 | 2026-02-12 | |
| NILE-3259 | Onboarding - Personal Details - Residents/TouristsOnboarding - Registration (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-03-06 | |
| NILE-3260 | Onboarding - Address Details - Residents/TouristsOnboarding - Registration (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-03-06 | |
| NILE-3261 | Onboarding - Financial Details - Residents/TouristsOnboarding - Registration (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-03-06 | |
| NILE-3292 | Profile & Settings- Landing Page | EDB | QA | Ready for QA | 18 | R1 | 2026-06-18 | |
| NILE-3295 | Profile & Setting- Language Selection | EDB | QA | Ready for QA | 18 | R1 | 2026-06-30 | |
| NILE-3296 | Profile & Settings- App AppearanceProfile & Settings - Landing Page | EDB | Definition | In Triage | — | R1 | 2026-06-30 | |
| NILE-3297 | Profile & Settings - Close Current Account (Terminate EZ Bank Relationship) | EDB | Definition | On hold | 18 | R1 | 2026-06-30 | |
| NILE-3298 | Profile & Settings- View Policies - Policies Landing | EDB | QA | Ready for QA | 18 | R1 | 2026-06-18 | |
| NILE-3299 | Profile & Settings- View Policies - Display T&Cs Details | EDB | QA | Ready for QA | 18 | R1 | 2026-06-18 | |
| NILE-3300 | Profile & Settings- View Policies - Update T&CProfile & Settings - View Policies (MOCK) | EDB | Definition | In Triage | — | R1 | 2026-06-07 | |
| NILE-3301 | Profile & Settings- View Policies - View Fees & Charges | EDB | QA | Ready for QA | 18 | R1 | 2026-06-07 | |
| NILE-3302 | Profile & Settings - Logout - App Log out | EDB | QA | Ready for QA | 18 | R1 | 2026-05-30 | |
| NILE-3305 | PWD - Device Accessibility Settings - Accessibility Labels Application | EDB | QA | Ready for QA | 18 | R1 | 2026-06-30 | |
| NILE-3306 | PWD - Device Accessibility Settings - View / Manage accessibility settings | EDB | QA | Ready for QA | 18 | R1 | 2026-07-15 | |
| NILE-3307 | PWD - Request Additional Support Services (Braille) - Request Braille Services | EDB | QA | Ready for QA | 18 | R1 | 2026-06-07 | |
| NILE-3319 | Origination - Username Creation | EDB | QA | QA Testing in process | 18 | R1 | 2026-03-12 | |
| NILE-3320 | Origination- Password Creation | EDB | QA | QA Testing in process | 18 | R1 | 2026-03-12 | |
| NILE-3321 | Origination- Biometric Login ActivationOnboarding - Create Credentials (MOCK) | EDB | Development | In Development | — | R1 | 2026-03-12 | |
| NILE-3322 | Origination – Mtablet QR CodeOnboarding - Assisted Enrollment (Mtablet) | EDB | Definition | In Triage | — | R1 | 2026-11-09 | |
| NILE-3323 | Origination - Retrieve ApplicationOnboarding - Retrieve Application (MOCK) | EDB | QA passed | QA test passed | 15 | R1 | 2026-03-12 |
User stories in Core Delivery, the same population the workflow above is drawn from. Tasks and technical tasks run a workflow with no test gates and are not counted anywhere on this page. “All Board Work” needs the items the task rule turns away, which delivery.csv does not carry.