As of 2026-08-13 · pulled 13 Aug 2026, 23:31 (same day as the last Jira change)

140 R1 user stories in Everyday Banking.

SummaryJira

No thresholds declared

21% of R1 user stories have passed QA, 86 are in flight, and 0 have reached SIT or beyond. Everyday Banking carries the most unfinished work between sprints, at 100% of sprint 17 scope.

  • “Delivered” means development complete and QA passed. 14 of these stories have since been released to production; the rest are not released — SIT, pre-production and release all come after it.
  • Every figure on this page counts user stories only, matching the workflow above. Delivery is executed on the technical tasks beneath a story, and those are not counted here — so this measures scope a business reader recognises, not effort spent.
R1 delivered

Development complete and QA passed. Not released.

R1 delivered

21%

29 of 140 R1 user stories

Completed in sprint 18

User stories whose completion date falls in sprint 18. The comparison is against sprint 17, which is complete, so part of the gap is time not yet elapsed.

Completed in sprint 18

0

Sprint 18 is still running

Carry-over

Sprint 17, the last completed sprint. In its final scope, not finished when it ended, and in a later sprint.

Carry-over

100%

78 of 78 in sprint 17 scope

▲ 2 vs sprint 16

Commitment reliability

Completed on or before the due date.

Coverage. 29 of 29 completed items carry a due date

Commitment reliability

0%

0 of 29 completed with a due date

Coverage 100%

Released to production

User stories with a recorded transition into the Production phase, at any point. Not stories sitting in it now — released work moves on to Complete, so the current count is zero and always will be. The programme figure beside it counts every issue type.

Released to production

14

of 140 R1 user stories · 568 work items across the programme

Stories blocked

Unfinished user stories on the receiving end of a Blocks or Depends link. What holds them up is counted whatever its type.

Coverage. See dependency coverage by squad

Stories blocked

12

0 blocked by another squad · 10 from outside the four

9% past QA, 0 in production nowJira

324 R1 stories, and how they moved through the workflow
How to read the workflow, and what it does not say
Every status the Jira workflow configures, in the order work walks them, for user stories — the population every figure on this page reports. Task and Technical Task run a workflow with no test gates, and mixing them made 88% of the apparent skips artefacts of the mix. A CIRCLE IS HOW MANY STORIES SIT THERE NOW. Filled means work is there; a tinted ring means work has been there and moved on; a dashed grey ring means no story has ever entered. That is why the release run reads zero and still shows traffic — nothing sits past QA test passed today, and stories have walked every status through to production. The chip beside each name is that status's own code, unique across the workflow so it identifies exactly one status wherever it is quoted, and coloured by its lifecycle phase so the eight groups still read at a glance. The legend below the diagram spells out all 28. A LINE TAKES THE COLOUR OF THE STATUS IT LEAVES, so a return is traceable to where it came from without following it. The main path is one constant width and the widest thing here; everything off it is thinner and weighted by how many moves took it. A dashed line with no motion is a route the workflow configures that no story has ever taken. Everything that fails, parks or reverts returns to In Triage or To Do, which is why those share one line back rather than six. No duration is shown anywhere on this diagram. 56% of status transitions in this project are zero-elapsed back-fill, so any median would measure when a status was typed rather than when work moved.
03849126056212300000000060005000000
GRGathering requirements
TRIIn Triage
TODOTo Do
DEVIn Development
PRVPeer review
RQAReady for QA
QATQA Testing in process
QAPQA test passed
REGIn regression testing
RSITReady for SIT
DSITDeployed to SIT
RPPReady for PreProd
DPPDeployed to PreProd
ARELApproved for release
SCHScheduled for release
PRODReleased to production
MONMonitoring
CMPComplete
RRVReady for review
IRVIn review
APVApproved
HLDOn hold
REOReopened
QAFQA test failed
REGFRegression failed
SITFSIT failednever used
PPFPreProd failednever used
RBKRollback

Definition38

  • GRGathering requirements0
  • TRIIn Triage38
  • RRVReady for review0
  • IRVIn review0
  • APVApproved0

Ready49

  • TODOTo Do49
  • REOReopened0

Development126

  • DEVIn Development126
  • PRVPeer review0

QA77

  • RQAReady for QA56
  • QATQA Testing in process21
  • QAFQA test failed0

Done29

  • QAPQA test passed23
  • CMPComplete6

SIT & Regression0

  • REGIn regression testing0
  • RSITReady for SIT0
  • DSITDeployed to SIT0
  • REGFRegression failed0
  • SITFSIT failednever used

Pre-production0

  • RPPReady for PreProd0
  • DPPDeployed to PreProd0
  • ARELApproved for release0
  • SCHScheduled for release0
  • PPFPreProd failednever used

Production0

  • PRODReleased to production0
  • MONMonitoring0
  • RBKRollback0

No single phase5

  • HLDOn hold5

User stories only — 324 of them, across the workflow's 28 statuses, with 1,349 moves between them. Task and Technical Task run a workflow with no test gates and are counted in the bar above but not here. The number in a circle is how many sit there NOW, not how many have passed through. Each chip is that status's own code, unique across the workflow so it can be quoted elsewhere, and coloured by its lifecycle phase. 65 moves went backwards and 63 left the road for a parked, failed or reverted state; every one of those returns to In Triage or To Do, which is why they share one line back.

14 stories released to production, 9% of R1 past QAJira

R1 — 21% past QA
QA passed, not released
Counts user stories at the last lifecycle phase. Some have since been released and the Summary carries that count, but this bar measures work that cleared development and test, not work that left the release chain.

29 of 140

R2 — 0% past QA
QA passed, not released
Counts user stories at the last lifecycle phase. Some have since been released and the Summary carries that count, but this bar measures work that cleared development and test, not work that left the release chain.

0 of 42

R3 — 0% past QA
QA passed, not released
Counts user stories at the last lifecycle phase. Some have since been released and the Summary carries that count, but this bar measures work that cleared development and test, not work that left the release chain.

0 of 56

68 carry no release

In none of these bars, and counted in the page total rather than distributed by guess.

The 10 epics carrying the most unfinished work
Ranked by open children, not by percentage
An epic at 20% with four children is a rounding error. Furthest phase reached is computed from the children IN SCOPE, so narrowing to a release changes it. Childless epics are excluded: a list about where the work is cannot be padded with epics carrying none.

The 10 epics with the most unfinished work, of 26 carrying any. 32 user stories are open across all of them.

An epic’s children here are its stories. The technical tasks beneath them are not counted, so this ranks epics by outstanding scope rather than by work remaining.

EpicSquadOpenChildrenQA passedFurthest phase reached
NILE-52Login - Forgot/Reset Credentials (MOCK)EDB4520%QA passed
NILE-62Multicurrency Accounts - Add Currency sub-Account (MOCK)EDB440%Definition
NILE-64Multicurrency Accounts - View transactions (MOCK)EDB440%Definition
NILE-44Onboarding - Registration (MOCK)EDB31377%QA passed
NILE-2243Multicurrency Accounts - View Account Details (MOCK)EDB330%Definition
NILE-1241Onboarding - Assisted Enrollment (Mtablet)EDB220%Definition
NILE-61Multicurrency Accounts - Open Account (MOCK)EDB220%Definition
NILE-196Profile & Settings - View Policies (MOCK)EDB110%Definition
NILE-197Profile & Settings - Landing PageEDB110%Definition
NILE-2252Multicurrency Accounts - Close / Delete Account (MOCK)EDB110%Definition

Sprint deliveryJira

Scope, reconciled · from Jira
An identity, not four measurements
Start plus added minus removed equals final, and it holds because added and removed are defined from the two boundary states rather than from raw join and leave events. An item that left and came back is committed scope that churned, not new scope. A build where they do not add up fails rather than renders.
Completed so far · from Jira
Counted from the completion date
Not the Sprint field. Stories are bulk-moved onto the active sprint, so the field would credit old completions to whichever sprint is running now.

0of 78 in scope

Sprint 18 is still running.

7 of the 16 open R1 activities are behind their own line, and ARB approved for Payments & Transfers is 55 points behind itManual entry

Where each release stands
Read a row across; the counts do not compare down
Within one kind of work the unit is the same in every release, so R1 build and R2 build compare. The COUNTS do not compare down a column: test cases run in the thousands where solution designs run in the tens, which is why there is no total. The SHARES do, and the bar draws the share rather than the count.
Kind of workRelease 1Release 2Release 3
Elaboration712 of 712100%348 of 44079%not started
Design gate86 of 12370%not startednot started
Build589 of 75578%not startednot started
Platform APIs0 of 50%not startednot started
Test cases4,332 of 6,19470%not startednot started
What was committed, and what arrived
Commitment against delivery, one kind of work per chart
The outline is what the squad signed up to at the start of the sprint; the solid bar is what it delivered. One kind of work per chart, because the units differ. Sprints are not slices of a total: work not finished is committed again next sprint, so these columns must never be added up.

Committed at the start of each sprint against what arrived. Both charts share one scale, so a bar in either stands for the same number of items.

CommittedDelivered

Build

12345678910111213141516171819

Design gate

131415161718
What is still open, and when it is due
Progress against the plan’s own line
Only activities incomplete against their own plan, grouped by the revised target they are working to. The gap is the share delivered minus the share of that activity’s window that has gone, both from the plan. An activity with no committed sprint has no window and shows no gap rather than a made-up one.

2026-09-014 of 6 behind their line

  1. ARB approvedP&Twell behind
  2. Experience APIsP&Twell behind
  3. Integration APIsP&Tbehind
  4. Front-end screensP&Tbehind
  5. Test casesP&Ton its line
  6. Test casesCLahead

2026-09-263 of 10 behind their line

  1. Experience APIsEDBwell behind
  2. ARB approvedCLbehind
  3. Integration APIsEDBbehind
  4. Experience APIsCLon its line
  5. Cyber reviewedCLon its line
  6. Front-end screensEDBahead
  7. Integration APIsCLahead
  8. Test casesEDBahead
  9. ARB approvedEDBahead
  10. Platform APIs: NICLno window

Measured against the plan’s own line. The bar is the share delivered; the tick is the share of that activity's own window that has gone, from its first committed sprint to its revised target. Both come from the plan. The gap between them is the number. The only judgement is where it becomes a word: behind past 5 points, well behind past 20.

Every activity the plan tracks
Delivered of committed, and what a dash means
On one sprint a cell reads as what the squad committed to on day one against what it finished. On all sprints it reads as progress against the whole plan. Over 100% is real and is not capped: a squad can finish more than it committed to. A dash is a row the plan holds with nothing committed; a dot is a row the squad does not have.
ActivityEveryday BankingCards & LendingPayments & TransfersValue Add
Elaboration
Regulatory review143 of 143 100%125 of 125 100%75 of 75 100%13 of 13 100%
UI/UX and customer journey29 of 29 100%31 of 31 100%15 of 15 100%3 of 3 100%
User stories114 of 114 100%94 of 94 100%60 of 60 100%10 of 10 100%
Design gate
ARB approved8 of 11 73%4 of 22 18%1 of 8 13%
Cyber reviewed11 of 11 100%13 of 22 59%8 of 8 100%
Solution design finalised11 of 11 100%22 of 22 100%8 of 8 100%
Build
Experience APIs37 of 71 52%18 of 22 82%42 of 63 67%
Front-end screens150 of 168 89%144 of 144 100%84 of 109 77%17 of 17 100%
Integration APIs27 of 62 44%47 of 64 73%23 of 35 66%
Platform APIs
Platform APIs: NI·0 of 5 0%·
Platform APIs: Payment Hub···
Platform APIs: T24··
Platform APIs: TPH···
Test cases
Test cases1,528 of 2,301 66%1,519 of 1,984 77%1,285 of 1,909 67%
Test cases including the deep layer

Squad and activity totals, not individual artefacts. The source is an aggregate grid, so this section cannot be drilled into.

PredictabilityJira

Carry-over
All three conditions, on a completed sprint
In the sprint’s final scope, not finished when it ended, and in a later sprint. Not “in more than one sprint” — a story can sit in two because someone corrected a field. Measured on completed sprints only: in a running sprint nothing has moved on yet and the figure reads near zero, which says carry-over is solved.

100%78 of 78 in sprint 17 scope

100%50%100%
  1. S12
  2. S13
  3. S14
  4. S15
  5. S16
  6. S17
Commitment reliability
Two denominators, named
Of completed user stories carrying a due date, the share that finished on or before it; stories completed without one are excluded from both halves rather than counted as met. The headline is every completed story to date and the line is each sprint’s own completions, so the endpoint and the figure above it are different measurements. At this population both denominators are small, so a single story moves the percentage a long way.

0%0 of 29 completed with a due date

100%50%0%
  1. S12
  2. S13
  3. S14
  4. S15
  5. S16
  6. S17

29 of 29 completed items carry a due date. The line is each sprint's own completions, the figure above is every completed item to date.

10% of work that reached Development came back to itJira

Development rework
Phase re-entries, not status hops
A move between two Development statuses is work continuing, not rework. The denominator is user stories that ever reached Development, so leaving work in Definition cannot improve the figure.

14%15 of 108 that reached Development

Nothing is ranked for attention, and why

Waiting on declared thresholds, not on build time. Solution Design’s 14 and 30-day bands are that page’s, not this one’s.

Where work is waiting, and why the dwell column is empty
Why the dwell column is empty
Median days in phase is not shown. 56% of status transitions in this project are zero-elapsed back-fill, so the figure would measure when a status was typed rather than when work moved.
PhaseItemsMedian days
Definition25
Ready7
Development2
QA77
SIT & Regression0
Pre-production0
Released to production0
QA passed29

Median days in phase is not shown. 56% of status transitions in this project are zero-elapsed back-fill, so the figure would measure when a status was typed rather than when work moved.

45 stories blocked, 21 of them from outside the four squadsJira

Blocked stories

12

unfinished stories on the receiving end of a link

Held by their own squad

2

a sequencing problem inside one team

Held by another squad

0

the only cross-squad constraint recorded

Held from outside the four

10

Integration, Workflow & Decision Engine, or work this page does not report

Who records dependencies, and who does not
Stories, not links, and coverage beside the count
Blocked means an unfinished user story on the receiving end of a Blocks or Depends link; Relates is narrative association and is excluded. One story held by four tickets is one thing to unblock — an earlier draft counted edges and overstated it by half. What does the blocking is counted whatever its type, because a story is usually held up by a technical task. A squad recording no links looks unblocked, which is why coverage is a column rather than a note.

12 unfinished user stories are blocked, by 40 links. No squad blocks another squad’s work, so there is no cross-squad matrix to draw. A further 25 work items outside these four squads are waiting on work inside them.

SquadOpen storiesWith any linkLink coverageBlocked
Everyday Banking14011683%12

InventoryJira

Filtering changes nothing above
This register lists the same user stories the sections above measure, so a row here is a row in every figure on the page. Narrowing it is display, never derivation: no figure above recomputes, and the count states how many of the population are showing so a filtered view cannot be mistaken for the whole.

Showing all 140 user stories.

KeySummarySquadPhaseStatusSprintReleaseDue
NILE-2190Onboarding– Personal Details (Egyptian Nationals – Unhappy Flow)Onboarding - Registration (MOCK)EDBQA passedComplete6R12026-02-12
NILE-2191Origination – Address Details (Egyptian Nationals – Unhappy Flow – Manual Update)Onboarding - Registration (MOCK)EDBQA passedQA test passed8R12026-02-12
NILE-2192Origination – Address Details (Egyptian Nationals – Unhappy Flow – Select From Map Update)Onboarding - Registration (MOCK)EDBQA passedQA test passed12R12026-02-12
NILE-2573Savings Account - Open (Account Benefits)EDBQAQA Testing in process18R12026-04-23
NILE-2574Savings Account - Open (Inputs & Success UI)Savings Account - Open savings account (MOCK)EDBQA passedQA test passed14R12026-04-23
NILE-2575Savings Account - View Account DetailsSavings Account - View account details (MOCK)EDBQA passedQA test passed14R12026-04-09
NILE-2576Savings Account - View Account Details (Tab)Savings Account - View account details (MOCK)EDBQA passedQA test passed11R12026-04-09
NILE-2577Savings Account - Share Account DetailsEDBQAQA Testing in process18R12026-04-09
NILE-2578Savings Account - View Account Details (Pledged Funds)EDBQAReady for QA18R12026-05-07
NILE-2579Savings Account - Generate StatementSavings Account - Generate statement (MOCK)EDBQA passedQA test passed12R12026-04-09
NILE-2580Savings Account - View Recent Transactions (Tab)Savings Account - View transactions (MOCK)EDBQA passedQA test passed14R12026-04-14
NILE-2581Savings Account - Search TransactionsSavings Account - View transactions (MOCK)EDBQA passedQA test passed14R12026-04-14
NILE-2582Savings Account - Filter TransactionsEDBQAQA Testing in process18R12026-04-17
NILE-2583Savings Account - Individual TransactionsEDBQAReady for QA18R12026-04-20
NILE-2584Savings Account - CloseEDBQAReady for QA18R12026-04-23
NILE-2590Current Account - Details PageEDBQAQA Testing in process18R12026-04-09
NILE-2591Current Account - View Account DetailsEDBQAQA Testing in process18R12026-04-09
NILE-2592Current Account - Share Account DetailsEDBQAQA Testing in process18R12026-04-09
NILE-2593Current Account - Generate StatementCurrent Account - Generate statement (MOCK)EDBQA passedQA test passed15R12026-04-09
NILE-2594Current Account - View Recent TransactionsEDBQAQA Testing in process18R12026-03-22
NILE-2595Current Account - Search/Filter TransactionsEDBQAQA Testing in process18R12026-03-22
NILE-2596Current Account - Filter TransactionsEDBQAQA Testing in process18R12026-03-18
NILE-2597Current Account - Individual TransactionsEDBQAQA Testing in process18R12026-03-21
NILE-2607Multi-currency Account - Open 1 (Account Benefits)Multicurrency Accounts - Open Account (MOCK)EDBDefinitionIn TriageR12026-07-08
NILE-2608Multi-currency Account - Open 2 (Account Specifications Input)Multicurrency Accounts - Open Account (MOCK)EDBDefinitionIn TriageR12026-07-09
NILE-2609Multi-currency Account - View Account DetailsMulticurrency Accounts - View Account Details (MOCK)EDBDefinitionIn TriageR12026-07-05
NILE-2610Multi-currency Account - View Account Details TabMulticurrency Accounts - View Account Details (MOCK)EDBDefinitionIn TriageR12026-07-08
NILE-2611Multi-currency Account - Share Account DetailsMulticurrency Accounts - View Account Details (MOCK)EDBDefinitionIn TriageR12026-07-11
NILE-2612Multi-currency Account - View Recent TransactionsMulticurrency Accounts - View transactions (MOCK)EDBDefinitionIn TriageR12026-08-13
NILE-2613Multi-currency Account - Search TransactionsMulticurrency Accounts - View transactions (MOCK)EDBDefinitionIn TriageR12026-08-13
NILE-2614Multi-currency Account - Filter TransactionsMulticurrency Accounts - View transactions (MOCK)EDBDefinitionIn TriageR12026-08-20
NILE-2615Multi-currency Account - Individual TransactionsMulticurrency Accounts - View transactions (MOCK)EDBDefinitionIn TriageR12026-08-20
NILE-2616Multi-currency Account - Generate StatementMulticurrency Accounts - Generate statement (MOCK)EDBDefinitionIn TriageR12026-08-28
NILE-2617Multi-currency Account - Add Money 1 (Details)Multicurrency Accounts - Add Currency sub-Account (MOCK)EDBDefinitionIn TriageR12026-07-22
NILE-2618Multi-currency Account - Add Money 2 (Doc Upload)Multicurrency Accounts - Add Currency sub-Account (MOCK)EDBDefinitionIn TriageR12026-07-24
NILE-2619Multi-currency Account - Add Money 3 (Review)Multicurrency Accounts - Add Currency sub-Account (MOCK)EDBDefinitionIn TriageR12026-07-26
NILE-2620Multi-currency Account - Add Money 4 (Success)Multicurrency Accounts - Add Currency sub-Account (MOCK)EDBDefinitionIn TriageR12026-07-29
NILE-2621Multi-currency Account - Send MoneyMulticurrency Accounts - Add Money (including FX) (MOCK)EDBDefinitionIn TriageR12026-08-10
NILE-2622Multi-currency Account - CloseMulticurrency Accounts - Close / Delete Account (MOCK)EDBDefinitionIn TriageR12026-09-08
NILE-2623Break Time Deposit Account - Explore alternative productsEDBQAReady for QA18R12026-05-01
NILE-2624Break Time Deposit Account - Important Notice bottom drawerEDBQAReady for QA18R12026-05-01
NILE-2625Break Time Deposit Account - Breakage TypeEDBQAReady for QA18R12026-05-02
NILE-2626Break Time Deposit Account - Review PageEDBQAReady for QA18R12026-05-02
NILE-2627Break Time Deposit Account - OTP InputEDBQAReady for QA18R12026-05-03
NILE-2628Break Time Deposit Account - Success PageEDBQAReady for QA18R12026-05-06
NILE-2630Break Certificate of Deposit Account - Explore alternative productsEDBQAReady for QA18R12026-05-06
NILE-2631 Break Certificate of Deposit Account - Important Notice bottom drawerEDBQAReady for QA18R12026-05-06
NILE-2632Break Certificate of Deposit Account - Breakage TypeEDBQAReady for QA18R12026-05-06
NILE-2633Break Certificate of Deposit Account - Review PageEDBQAReady for QA18R12026-05-06
NILE-2634Break Certificate of Deposit Account - OTP InputEDBQAReady for QA18R12026-05-06
NILE-2635Break Certificate of Deposit Account - Success PageEDBQAReady for QA18R12026-05-06
NILE-2636Open Time Deposit Account - Account BenefitsEDBQAReady for QA18R12026-05-07
NILE-2637Open Time Deposit Account - Account SpecificationsEDBQAReady for QA18R12026-05-07
NILE-2638Open Time Deposit Account - Interest & RenewalEDBQAReady for QA18R12026-05-07
NILE-2639Open Time Deposit Account - Review PageEDBQAReady for QA18R12026-05-07
NILE-2640 Open Time Deposit Account - Success PageEDBQAReady for QA18R12026-05-07
NILE-2641Open Certificate of Deposit Account - Accounts BenefitsEDBQAQA Testing in process18R12026-05-07
NILE-2642Open Certificate of Deposit Account - Account SpecificationsEDBQAReady for QA18R12026-05-07
NILE-2643Open Certificate of Deposit Account - Interest & RenewalEDBQAReady for QA18R12026-05-07
NILE-2644Open Certificate of Deposit Account - Review PageEDBQAReady for QA18R12026-05-07
NILE-2645Open Certificate of Deposit Account - Success PageEDBQAReady for QA18R12026-05-07
NILE-2646Certificate of Deposit Generate StatementEDBQAReady for QA18R12026-05-07
NILE-2647Certificate of Deposit View Account DetailsEDBQAReady for QA18R12026-06-30
NILE-2648Time Deposit View Account DetailsEDBQAReady for QA18R12026-05-07
NILE-2649Time Deposit View Account Details TabEDBQAReady for QA18R12026-05-07
NILE-2652Certificate of Deposit Account View Recent TransactionsEDBQAReady for QA18R12026-06-15
NILE-2653Certificate of Deposit Account Search TransactionsEDBQAReady for QA18R12026-06-17
NILE-2654Certificate of Deposit Account Filter Transactions EDBQAReady for QA18R12026-06-19
NILE-2655Certificate of Deposit Account Individual TransactionsEDBQAReady for QA18R12026-06-21
NILE-2656Time Deposit Account View Recent TransactionsEDBQAReady for QA18R12026-06-23
NILE-2657Time Deposit Account Search TransactionsEDBQAReady for QA18R12026-06-24
NILE-2658Time Deposit Account Filter Transactions EDBQAReady for QA18R12026-06-27
NILE-2659Time Deposit Account Individual TransactionsEDBQAReady for QA18R12026-06-29
NILE-2661Origination- Account Opening – Email NotificationEDBQAReady for QA18R12026-03-12
NILE-2662Origination- Account Opening Success PageEDBQAQA Testing in process18R12026-03-12
NILE-2663Origination - Missing Documents (KYC)Onboarding - AML / Enhanced Due Diligence (System Integration)EDBQAQA Testing in process13R12026-03-12
NILE-2664Origination - AML Adjudication (Bank)Onboarding - AML / Enhanced Due Diligence (MOCK)EDBQA passedQA test passed12R12026-03-12
NILE-2665Origination - Enhanced Due DiligenceEDBQAQA Testing in process18R12026-03-12
NILE-2771Origination – Financial Information (Egyptian Nationals – Happy Flow):Onboarding - Registration (MOCK)EDBQA passedComplete7R12026-02-12
NILE-2772Origination – Financial Information (Egyptian Nationals – Unhappy Flow):Onboarding - Registration (MOCK)EDBQA passedQA test passed12R12026-02-12
NILE-3259Onboarding - Personal Details - Residents/TouristsOnboarding - Registration (MOCK)EDBDefinitionIn TriageR12026-03-06
NILE-3260Onboarding - Address Details - Residents/TouristsOnboarding - Registration (MOCK)EDBDefinitionIn TriageR12026-03-06
NILE-3261Onboarding - Financial Details - Residents/TouristsOnboarding - Registration (MOCK)EDBDefinitionIn TriageR12026-03-06
NILE-3292Profile & Settings- Landing PageEDBQAReady for QA18R12026-06-18
NILE-3295Profile & Setting- Language SelectionEDBQAReady for QA18R12026-06-30
NILE-3296Profile & Settings- App AppearanceProfile & Settings - Landing PageEDBDefinitionIn TriageR12026-06-30
NILE-3297Profile & Settings - Close Current Account (Terminate EZ Bank Relationship)EDBDefinitionOn hold18R12026-06-30
NILE-3298Profile & Settings- View Policies - Policies LandingEDBQAReady for QA18R12026-06-18
NILE-3299Profile & Settings- View Policies - Display T&Cs DetailsEDBQAReady for QA18R12026-06-18
NILE-3300Profile & Settings- View Policies - Update T&CProfile & Settings - View Policies (MOCK)EDBDefinitionIn TriageR12026-06-07
NILE-3301Profile & Settings- View Policies - View Fees & ChargesEDBQAReady for QA18R12026-06-07
NILE-3302Profile & Settings - Logout - App Log outEDBQAReady for QA18R12026-05-30
NILE-3305PWD - Device Accessibility Settings - Accessibility Labels ApplicationEDBQAReady for QA18R12026-06-30
NILE-3306PWD - Device Accessibility Settings - View / Manage accessibility settingsEDBQAReady for QA18R12026-07-15
NILE-3307PWD - Request Additional Support Services (Braille) - Request Braille ServicesEDBQAReady for QA18R12026-06-07
NILE-3319 Origination - Username CreationEDBQAQA Testing in process18R12026-03-12
NILE-3320Origination- Password CreationEDBQAQA Testing in process18R12026-03-12
NILE-3321Origination- Biometric Login ActivationOnboarding - Create Credentials (MOCK)EDBDevelopmentIn DevelopmentR12026-03-12
NILE-3322Origination – Mtablet QR CodeOnboarding - Assisted Enrollment (Mtablet)EDBDefinitionIn TriageR12026-11-09
NILE-3323Origination - Retrieve ApplicationOnboarding - Retrieve Application (MOCK)EDBQA passedQA test passed15R12026-03-12
Showing 100 of 140 matching.

User stories in Core Delivery, the same population the workflow above is drawn from. Tasks and technical tasks run a workflow with no test gates and are not counted anywhere on this page. “All Board Work” needs the items the task rule turns away, which delivery.csv does not carry.